Like most websites, we use cookies and other similar technologies for a number of reasons, such as keeping our website reliable and secure, personalizing content, providing social media features and to better understand how our site is used. By using our site, you are agreeing to our use of these tools. Learn More

Implementation Timeline and Activity Definitions

Planned Go-Live is November 2020

Go-Live Timeline

Implementation Phases

  • Phase 0 - Pre-work (July 1, 2019 - August 30, 2019)
  • Phase 1 - Direction (September 2, 2019 - November 1, 2019)
  • Phase 2 - Readiness and Clinical System Review (November 4, 2019 - February 28, 2020)
  • Phase 3 - Testing (March 2, 2020 - August 28, 2020)
  • Phase 4 - End User Training, Deployment, and Go-Live (August 31, 2020 - October 30, 2020)
  • Go-Live - November 1, 2020
  • Phase 5 - Post-Live Support and Optimization (November 16, 2020 - January 22, 2021)